(Summary description)The construction unit entrusted Sichuan Jinmei Environmental Protection Co., Ltd. to undertake the "technical transformation project of laterite nickel mine process development and verification test line" environmental impact report preparation. The project has carried out the first environmental impact assessment announcement.
The second public announcement of the environmental impact assessment of the laterite nickel mine process development and verification test line of Sichuan Shunying Power Battery Materials Co., Ltd.
The construction unit entrusted Sichuan Jinmei Environmental Protection Co., Ltd. to undertake the "technical transformation project of laterite nickel mine process development and verification test line" environmental impact report preparation. The project has carried out the first environmental impact assessment announcement. The preliminary results of the environmental impact assessment work have been obtained. According to the "Measures for Public Participation in Environmental Impact Assessment" (Ministry of Ecology and Environment Order No. 4), the relevant environmental impact assessment information is now announced as follows:
I. Overview of the construction project
1. Project name: Technological transformation project of laterite nickel mine process development and verification test line
2. Nature of construction: technological transformation
3. Construction address: Jinxiang Chemical Industrial Park, Meishan City
4. Project investment: total investment of 11 million yuan
5. Construction content and scale: Upgrading and transforming the laterite nickel mine test line technological transformation project, with a total construction area of 1250m2, is a pilot project, divided into three sections: wet process zone, magnesium nitrate decomposition zone and nitric acid conversion zone.
6. Introduction to existing projects: The company now has a nickel sulfate production line, a cobalt tetroxide production line (not produced), and a ternary precursor material production line (5000t/a production capacity). Waste gas: the sulfuric acid mist generated in the slurrying process is collected and purified by the alkaline water spray system and discharged from a 15m high exhaust cylinder; the sulfuric acid mist generated in the leaching process is collected and purified by the alkaline water spray system and then discharged from 15m High exhaust cylinder discharge; the sulfuric acid mist generated in the impurity removal process is collected and purified by the alkaline water spray system and discharged from the 15m high exhaust cylinder; the sulfuric acid mist and VOCs generated in the extraction process are subjected to alkali spray + UV photocatalysis +The activated carbon is adsorbed and discharged through a 15m exhaust cylinder; the ammonia produced in the ternary drying process is discharged from a 15m high exhaust cylinder after water absorption reaches the standard; the ammonia produced by the alkali recovery system is discharged from a 15m high exhaust cylinder after water absorption reaches the standard emission. Wastewater: The production wastewater is discharged into the sewage treatment plant of the park after being treated by the sewage treatment station in the plant area; the domestic sewage enters the sewage treatment plant of the park after pretreatment. Solid waste: the destination of various solid waste pollutants is clear.
2. The possible impact of the construction project on the environment
Exhaust gas: The air pollutants produced by this project are mainly reactor leaching exhaust gas, natural gas combustion exhaust gas, magnesium nitrate calcining exhaust gas, and storage tank area exhaust gas;
Wastewater: No production waste water is generated in the production process of this pilot project; the ground is cleaned with brooms, no water is used, and no washing waste water is generated; no new labor force is added in the factory area, all are deployed from the existing factory area, and there is no living Sewage is generated; circulating cooling water relies on the existing circulating cooling pool in the plant area, without circulating cooling water discharge. It can be seen that the wastewater involved in this project is mainly reactor equipment cleaning water, lye absorption tower drainage and water spray tower drainage;
Solid waste: General solid waste is the large-particle laterite ore collected and sorted out by the bag filter, waste packaging materials, hazardous waste is unqualified pilot products, waste engine oil, waste lubricating oil, oily gloves, oily rags, etc. . ;
Noise: The noise produced is mainly the noise of various equipment in the factory.
3. Countermeasures and measures to prevent or reduce adverse environmental impacts
1. Water pollution prevention and control measures
The wastewater involved in this project is mainly reactor equipment cleaning water, lye absorption tower drainage and water spray tower drainage. The produced production wastewater (mainly waste gas washing water) enters the existing sewage treatment system of the plant, and its treatment process is "air flotation + sedimentation tank + resin adsorption + catalytic oxidation removal of COD + membrane treatment system + MVR evaporation and concentration". After the treatment meets the indirect discharge standard in Table 1 of the "Inorganic Chemical Industry Pollutant Discharge Standard" (GB31573-2015), it will be treated in the wastewater treatment plant of the park, and finally discharged into the Liquan River.
For the prevention and control of groundwater pollution in the project, the environmental impact assessment requires the construction unit to adhere to the principle of “source control, end prevention, pollution monitoring, and emergency response combined”, and take effective anti-seepage measures without affecting the groundwater environment in the area.
2. Waste gas pollution prevention and control measures
Leached nitric acid mist (characterized by NOx) and nitric acid storage tank. Nitric acid mist enters the lye absorption tower through the exhaust valve through the pipeline for absorption treatment, and is discharged through a 15m exhaust tube (1# exhaust tube), and then the calcining and decomposing furnace The generated exhaust gas enters the “cyclone dust collector + bag filter + water spray tower" through the exhaust pipe and is discharged through a 15m exhaust tube (2# exhaust tube) after treatment. The natural gas combustion exhaust gas of the calciner passes through 1 An 8m exhaust pipe discharges. .
To sum up, it can be seen that the external exhaust gas of this project has a small impact on the regional atmospheric environment, and will not change the regional atmospheric environmental function due to the project construction.
3. Noise control measures
This project selects low-noise equipment, adopts shock absorption and sound insulation measures for the foundation of high-noise equipment, and controls the impact of noise on the surrounding environment through the reasonable layout of various devices and buildings. After the above measures are taken, the noise at the plant boundary can be reduced. Meet relevant requirements.
4. Solid waste prevention measures
The solid waste generated by this project can be comprehensively utilized and properly disposed of, and will not cause secondary pollution.
Four, the main points of the preliminary conclusions of the environmental impact assessment
This project complies with the national industrial development policy, the site selection complies with the relevant planning, there are no obvious environmental constraints, and the overall layout is reasonable. The pollutants generated during the operation period of the project shall be treated and controlled according to the measures and plans proposed in this report, strictly implemented the "three simultaneous" system, and strengthened internal management to realize the stable operation of environmental protection facilities to ensure pollution Under the premise of meeting the discharge standards, the project will not have a significant impact on the surrounding environment. The construction of this project can promote local economic development and has good social and economic benefits. From the perspective of environmental protection, this project is feasible.
V. Internet links to the draft environmental impact report for comments and ways and means to access the paper report
Please refer to Attachment 1 for the draft of the environmental impact report for comments.
Methods and means for accessing the paper report: Follow the contact information of the construction unit to access the paper report.
Name and contact information of the construction unit:
Construction unit: Sichuan Shunying Power Battery Material Co., Ltd.
Contact address: Jinxiang Chemical Industrial Park, Meishan City
Contact: Mr. Gao Phone: 13980377147
Name and contact information of the environmental impact assessment agency:
Evaluation unit: Sichuan Jinmei Environmental Protection Co., Ltd.
Contact address: No. 166, Jinshi Road, Jinjiang District, Chengdu
Contact person: Li Gong Phone: 18081190780
Six. Public scope for soliciting opinions
The scope of soliciting public opinions is mainly the opinions and requirements of the people or social groups around the project (including village committees, enterprises and institutions, etc.) on the environmental protection aspects of the construction project.
(1) Are you satisfied with the environmental impact prevention measures caused by this project?
(2) Are you satisfied with the discharge of pollutants after a series of environmental protection measures have been adopted in this project?
(3) In your opinion, are there any environmental impact factors that have not been fully considered in this environmental impact assessment? Or what needs to be improved?
7. Web link to the public comment form
See Annex 2 for the public comment form.
8. Ways and means for the public to put forward opinions
Relevant opinions and suggestions on the environmental protection of the project construction can be submitted to the construction unit by letter, fax, e-mail or other methods provided by the construction unit within the specified time, and reflect the environmental impact of the construction unit. Relevant comments and suggestions.
When the public submits comments, please provide effective contact information; encourage the use of real-name submissions and provide permanent address. Regarding the relevant personal information submitted by the public, our company promises that it will not be used for purposes other than public participation in the environmental impact assessment.
9. The start and end time for public comments
Within 10 working days from the date of this public announcement.
MORE NEWS
Sichuan Shunying Power Battery Material Co., Ltd.
Tel:028-38662031
Add:No. 1, Jinhua Road, Meishan High-tech Industrial Park, Dongpo District, Meishan City, Sichuan Province
© COPYRIGHT 2021 Sichuan Shunying Power Battery Material Co., Ltd.. ALL RIGHTS RESERVED 蜀ICP备2021007096号 Powered by 300.cn